July 10 2019
What is the procedure of installing the PBR?
The PBR arrives in 4 components: water pre-treatment tank, the top light, temperature control unit and the algae culture chamber (photobioreactor) itself. Simply place and level the components, connect the water supply, interconnect the components disconnected for shipping, and plug it all in. It generally takes 3-4 hours to get it uncrated, leveled, and installed. We also offer an optional installation and training package. This includes a technician from Industrial Plankton visiting your facility, installing the equipment, and walking through algae culturing (from flask to the bioreactor’s operation). This option is not required for clients who are already skilled algae technicians.